Wrt power source and NA5 to be detail trouble shooting chart to be prepared and discussed
Niraj to take lead
Wrt power source and NA5 to be detail trouble shooting chart to be prepared and discussed
Niraj to take lead
Abnormal sound observed when 50 t inside crane moves above vtl
Niraj please make check list for both transformer and aur, get it sign off and carry out pm as per same .
Vaibhav as discussed please prepare opl, for cleaning flex recovery cylinder and explain to operator and line engineer
Pipe was required to be cut as per actual requirement, and provision for rounding off was required to be done as explained to alpesh
As per admin confirmation all toilet need to be painted
Amit pl ensure
Do oil testing of crane gear box and take decision of replacement
Of coil shop and panel shop crane
Td - 21-2-2017
I install emergancy hooter at admin
Hooter reached , cable awaited., Cable expected to reach by Monday.
Work needs to be completed by 22-2-207